The original steel version of the Crum Creak Viaduct was built in 1895, spanned 915 feet and stood 100 feet high. The bridge carries over 3 million passengers annually with 320 passenger trains each week along the Media/Elwyn Line into and out of Center City Philadelphia. The bridge needed replacement, but that work had to cause as little commuter disruption as possible. Therefore, the work was timed to only take 11 weeks from demolition to reconstruction and restoration of service.

Carr & Duff, Inc. was tasked with providing and maintaining temporary power for the site, demolition of all aerial cables and installation of new conduits, cable, catenary support steel as well as grounding of the new structure for SEPTA’s Crum Creek Viaduct replacement.

During construction, Carr & Duff, Inc. provided an 1,800-foot-long high voltage temporary service from nearby Swarthmore College to the construction site, and subsequently removed the service at the end of the project. Before demolition, the existing electric infrastructure had to be removed, including more than two miles of SEPTA’s 24,000 volt transmission lines, aerial signal and communication cables, messenger cables and two tracks of overhead catenary cables and support hardware for each of the mile-long track sections.

The new bridge was built with accelerated bridge construction techniques, designed to match the existing alignment and minimizing effects on the existing viaduct structure while it remained in-service. Substructures were built adjacent to the existing bridge, temporary brackets were erected and new girders and the deck were constructed on the temporary brackets. During the outage and after the old bridge was demolished, the general contractor performed a lateral slide of the new structure.

Carr & Duff, Inc. crews installed 6,000 feet of four-inch rigid steel conduit and 1,400 feet of six-inch rigid steel conduit from two 125-foot lifts. The conduits, support racks and junction boxes were all installed along the underside of the new structure, suspended 100 feet above the Crum Creek.

To replace the previous bridge’s cable, Carr & Duff, Inc. installed new aerial high voltage power and signal cables. Altogether, 9,800 feet of signal, communication and messenger cables were installed as well as catenary support steel, and insulators on both tracks.

During the 11-week construction period, Carr & Duff, Inc. crews worked in two shifts. The work was completed on-time and rail services resumed in fall, 2016.

Latest Safety News

Winslow Elementary School Storm Response

Winter 2017 was not as severe as winters past on the east coast but we still had our fair share of storms. Being well equipped with the equipment and manpower to get the job done is what makes us stand out during destructive storms. Our expertise was needed in upstate...

read more

Our Recent Safety Committee Discussions

Carr & Duff, Inc. utilizes a Safety Committee made up of field and office personnel. The committee meets monthly to discuss and review issues or items that need to be addressed within the company. The committee is empowered to facilitate change when warranted to...

read more

Philadelphia’s YouthBuilds Charter School

On November 16th, 2016 Carr & Duff, Inc.’s Safety Department taught an “Electrical Safety in Construction” course at Philadelphia’s YouthBuilds Charter School. Carr & Duff, Inc.’s Safety Director, Wayne Sottung taught the interested students about the...

read more

Recent Projects

Temple Health – Jeanes Hospital Substation (2018)

Working with our General Contractor, Carr & Duff, Inc. constructed a new substation building...

Trenton Makes the World Takes (2018)

In August 1917 a historic and iconic sign was installed on the Lower Trenton Toll Bridge, and 100...

Pemberton Borough Utility Distribution Relocation (2018)

Carr & Duff, Inc was tasked with a design-build utility relocation project for the Borough of...

Quick Contact